Village negotiates with Ohio EPA over wastewater plant
By Lauren Heaton
The Village wastewater treatment plant has been cited by the Ohio Environmental
Protection Agency for noncompliance with the regulations of its federal
permit. Village Council learned of the citation during an executive
session at its June 16 meeting, three months after the citation was
issued. Council agreed after that meeting to hire an environmental attorney
to work with the EPA to bring the plant back into compliance with the
Ohio Revised Code.
“We’re trying to work with the EPA, and we’re seeking
to be in compliance with the EPA as fast as we possibly can,”
Council member Lori Askeland said last week.
Village Council learned about the Ohio EPA’s citation from newly
appointed Interim Village Manager John Weithofer at the June 16 meeting.
Ohio EPA Director Chris Korleski informed the Village in a draft order
dated April 8 to then Village Manager Eric Swansen that the Village
had violated its National Pollutant Discharge Elimination System permit
by exceeding effluent limits on several occasions and failing to meet
deadlines for necessary improvements to the plant.
The order proposed that the Village pay a fine of $76,779 and agree
to meet a compliance schedule to bring the plant up to date by next
year. The compliance schedule included establishing engineering plans
within three months of receipt of the order, beginning construction
within three months of that deadline and completing construction within
nine months of breaking ground. The order also requested that the Village
review the proposal and respond within 21 days to resolve the matter.
According to Askeland, though Council members were never informed of
the EPA’s order, they were aware of ongoing correspondence between
the Village and the EPA regarding a longstanding need for approximately
$2.2 million in improvements to the plant that had been delayed for
several years due to budgetary constraints. Council had agreed in December
2007 to use $1.2 million from an Ohio Public Works Commission Issue
2 grant, which would become available in 2009, and loans to pay for
the improvements. Swansen had said at that time that the Village would
apply for an extension to the EPA’s September 2008 compliance
deadline.
In the meantime, the plant’s violations continued and eventually
went to enforcement by the EPA, which resulted in the April letter from
the director. The violations included a total of 127 incidents from
January 2006 to December 2007 during which higher than legal levels
of pollutants such as phosphorus, mercury, fecal coliform and chlorine
were detected in the plant’s effluent. The violations occurred
largely during heavy rains, which increased the total effluent beyond
the plant’s capacity, causing nearly raw sewage to be discharged
into the waters of Glen Helen and beyond.
Swansen did reply to the EPA’s draft order to request an extension
on the response deadline, which the EPA granted until June 20, Askeland
said. Council members learned this four days before the response was
due, at which point Village Solicitor John Chambers advised them to
retain Tim Hoffman, an environmental attorney from his firm Coolidge,
Wall, Womsley & Lombard, to work with the EPA.
According to Chambers, the Village is scheduled to meet with the EPA
sometime this month to outline a schedule that satisfies the needs and
abilities of both parties to get the plant in compliance.
Attorneys from both sides are also discussing the civil penalties, Chambers
said. According to Ohio EPA spokesperson Mike Settles, the EPA is generally
open to negotiating civil penalties, which can sometimes be waived in
exchange for additional plant improvements or other environmental projects.
Though a draft order from the EPA is an item that Askeland said would
generally be wise to share with Council, she and other Council members
are more focused on trying to resolve the current issue than trying
to figure out exactly why the order came as a surprise to them.
“We feel quite confident in the people we’re working with,
and we feel we’ll be able to solve the problem,” she said.
Contact: lheaton@ysnews.com